Contents
1.4 Contact
information for the Project
1.5 Summary
of Construction Works
1.6 Summary
of EM&A Programme Requirements
2 Environmental
Monitoring and Auditing
2.1.2
Summary of Monitoring Results
2.2.2
Summary of Monitoring Results
2.4.2
Summary of Monitoring Results
2.4.3
Marine Sediment Management
2.5 Chinese
White Dolphin Monitoring
2.5.1
Summary of Monitoring Results
2.6 Environmental
Site Inspection
2.6.1
Landscape and Visual Mitigation Measures
2.6.2
Land Contamination Assessment
2.7 Audit
of SkyPier High Speed Ferries
2.8 Audit
of Construction and Associated Vessels
2.9 Review
of the Key Assumptions Adopted in the EIA Report
3 Report on
Non-compliance, Complaints, Notifications of Summons and Prosecutions
3.1 Compliance
with Other Statutory Environmental Requirements
3.2 Analysis
and Interpretation of Complaints, Notification of Summons and Status of
Prosecutions
3.2.2
Notifications of Summons or Status of Prosecution
4 Conclusion
and Recommendation
Table
1.1: Contact Information of Key Personnel
Table
1.2: Contact Information of the Project
Table
1.3: Summary of Status for All Environmental Aspects under the Updated EM&A
Manual
Table
2.1: Impact Air Quality Monitoring Stations
Table
2.2: Percentage of Air Quality Monitoring Results within Action and Limit
Levels
Table
2.3: General Meteorological Condition during Impact Air Quality Monitoring
Table
2.4: Impact Noise Monitoring Stations
Table 2.5: Percentage of Noise Monitoring Results within
Action and Limit Levels
Table
2.6: General Meteorological Condition during Impact Noise Monitoring
Table
2.7: Action and Limit Levels for Construction Waste
Table
2.8: Construction Waste Statistics
Table 2.10: Summary of Photo Identification
Table
2.11: Landscape and Visual – Construction Phase Audit Summary
Table
2.13: Summary of the Transplanted Trees Updated in the Reporting Period
Table
2.14: Photos of the Existing Transplanted Trees Inspected in the Reporting
Period
Table
3.1: Summary of Environmental Complaints
Table
3.2: Statistics for Valid Exceedances for the Environmental Monitoring
Table
3.3: Statistics for Non-compliance, Complaints, Notifications of Summons and
Prosecution
Figures
Appendices
Environmental Mitigation Implementation Schedule (EMIS) for Construction Phase |
|
3RS |
Three-Runway System |
AAHK |
Airport Authority Hong Kong |
AECOM |
AECOM Asia Company Limited |
AFCD |
Agriculture, Fisheries and
Conservation Department |
AIS |
Automatic Information System |
ANI |
Encounter Rate of Number of
Dolphins |
APM |
Automated People Mover |
AW |
Airport West |
BHS |
Baggage Handling System |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CTCC |
Construction Traffic Control
Centre |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DEZ |
Dolphin Exclusion Zone |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EM&A |
Environmental Monitoring &
Audit |
EMIS |
Environmental Mitigation
Implementation Schedule |
EP |
Environmental Permit |
EPD |
Environmental Protection
Department |
EPSS |
Emergency Power Supply Systems |
ET |
Environmental Team |
FCZ |
Fish Culture Zone |
HDD |
Horizontal Directional Drilling |
HKBCF |
Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing Facilities |
HKIA |
Hong Kong International Airport |
HSF |
High Speed Ferry |
IEC |
Independent Environmental
Checker |
I-2RS |
Interim Two Runway System |
LKC |
Lung Kwu Chau |
MMHK |
Mott MacDonald Hong Kong Limited |
MMWP |
Marine Mammal Watching Plan |
MSS |
Maritime Surveillance System |
MTRMP-CAV |
Updated Marine Travel Routes and
Management Plan for Construction and Associated Vessel |
NEL |
Northeast Lantau |
NLMP |
North Lantau Marine Park |
NWL |
Northwest Lantau |
PAM |
Passive Acoustic Monitoring |
SC |
Sha Chau |
SCZ |
Speed Control Zone |
SCLKCMP |
Sha Chau and Lung Kwu Chau
Marine Park |
SS |
Suspended Solids |
STG |
Encounter Rate of Number of
Dolphin Sightings |
SWL |
Southwest Lantau |
T2 |
Terminal 2 |
The Manual |
The Updated EM&A Manual |
The Project |
The Expansion of Hong Kong
International Airport into a Three-Runway System |
The SkyPier Plan |
Marine Travel Routes and
Management Plan for High Speed Ferries of SkyPier |
TSP |
Total Suspended Particulates |
WL |
West Lantau |
WMP |
Waste Management Plan |
The
“Expansion of Hong Kong International Airport into a Three-Runway System” (the Project)
serves to meet the future air traffic demands at Hong Kong International
Airport (HKIA). On 7 November 2014, the Environmental Impact Assessment (EIA)
Report (Register No.: AEIAR-185/2014) for the Project was approved and an
Environmental Permit (EP) (Permit No.: EP-489/2014) was issued for the
construction and operation of the Project.
Airport
Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK)
to undertake the role of Environmental Team (ET) for carrying out the
Environmental Monitoring & Audit (EM&A) works during the construction
phase of the Project in accordance with the Updated EM&A Manual (the
Manual).
This
is the 37th Construction Phase Quarterly EM&A Report for the
Project which summarises the monitoring results and audit findings of the
EM&A programme during the reporting period from 1 January 2025 to 31 March
2025.
The new North Runway was commissioned in November 2022. Following the completion of reconfiguration works on the
Centre Runway, the Three-runway System (3RS) was commissioned on 28 November
2024.
Key
Activities in the Reporting Period
The key
activities of the Project carried out in the reporting period are located in
reclamation areas and existing airport island respectively. Works in the
reclamation areas included
filling works, pavement works, concourse superstructure works, tunnel works for Automated People Mover
(APM) and Baggage Handling System (BHS) and associated works. Meanwhile, works
on the existing airport island involved Terminal 2 (T2) expansion works,
modification and tunnel works for APM and BHS, utilities works, road and
drainage works, excavation works and 132kV cable
laying works.
EM&A
Activities Conducted in the Reporting Period
The EM&A programme was undertaken in accordance with the Manual of the Project. Summary of the monitoring activities during this reporting period is presented as below:
Monitoring Activities |
Number of Sessions |
1-hour Total Suspended Particulates (TSP) air quality monitoring |
90 |
Noise monitoring |
50 |
Vessel line-transect surveys for operation phase Chinese White Dolphin (CWD) monitoring |
6 |
Environmental
auditing works, including weekly site inspections of construction works
conducted by the ET and bi-weekly site inspections conducted by the Independent
Environmental Checker (IEC), audit of SkyPier High Speed Ferries (HSF), and
audit of construction and associated vessels, were conducted in the reporting
period. Based on the
information including ET’s observations, records of Maritime Surveillance
System (MSS), and contractors’ site records, it is noted that environmental
pollution control and mitigation measures were properly implemented and
construction activities of the Project in the reporting period did not
introduce adverse impacts to the sensitive receivers.
A 12-month
operation phase CWD monitoring by vessel line transect survey was commenced in
January 2025.
Snapshots of Good Environmental
Practices in the Reporting Period
|
|
|
Wheel washing at site exit |
Provision of environmental training for site personnel |
Self-monitoring of effluent sample from wastewater treatment facility |
Key examples of good site practices implemented
in the Project are highlighted as below:
1.
Provision of wheel washing for construction vehicles before leaving the
site area.
2. Provision
of environmental training for site personnel by the contractor.
3. Conducted self-monitoring
of an effluent sample from the wastewater treatment facility by the contractor.
Summary Findings of the EM&A Programme
The monitoring works for construction
dust, construction noise, construction waste and landscape & visual were
conducted during the reporting period in accordance with the Manual.
Monitoring results of construction
dust, construction noise, and construction waste did not trigger the
corresponding Action and Limit Levels in the reporting period. No
non-conformity was recorded for landscape & visual monitoring in the
reporting period.
The key findings of the EM&A programme during the reporting period are summarised as below:
|
Yes |
No |
Details |
Analysis / Recommendation / Remedial
Actions |
Breach of Limit Level^ |
|
√ |
No breach of Limit Level was recorded. |
Nil |
Breach of Action Level^ |
|
√ |
No breach of Action Level was recorded. |
Nil |
Complaint received in this reporting period |
√ |
|
A complaint regarding dust nuisance was received on 14
January 2025. |
ET requested the relevant contractor to provide information
regarding the complaint and replies indicated cleaning works were carried out
inside the North Wing Level 6 of Terminal 2 Concourse. The relevant
contractor improved their dust mitigation measures prior to undertaking
further cleaning works at the area and conducted refresher training for
frontline workers. During the ET’s site inspections, no dust related item was
recorded. The relevant contractor was reminded to keep review and enhance
relevant dust suppression measures to prevent dust nuisance. Hence, the case
was considered closed. |
Notification of any summons and status of prosecutions |
|
√ |
No notification of summons nor prosecution was received. |
Nil |
Changes that affect the EM&A |
|
√ |
There was no change to the construction works that may
affect the EM&A. |
Nil |
Remarks:
^Only triggering of Action or Limit Level found related to Project works is counted as Breach of Action or Limit Level.
On 7
November 2014, the Environmental Impact Assessment (EIA) Report (Register No.:
AEIAR-185/2014) for the “Expansion of Hong Kong International Airport into a
Three-Runway System” (the Project) was approved and an Environmental Permit
(EP) (Permit No.: EP-489/2014) was issued for the construction and operation of
the Project.
Airport
Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK)
to undertake the role of Environmental Team (ET) for carrying out the
Environmental Monitoring & Audit (EM&A) works during the construction
phase of the Project in accordance with the Updated EM&A Manual (the
Manual) submitted under EP Condition 3.1[1]. AECOM Asia Company Limited (AECOM) was
employed by AAHK as the Independent Environmental Checker (IEC) for the
Project.
The
Project covers the expansion of the existing airport into a three-runway system
(3RS) with key project components comprising land formation of about 650 ha and
all associated facilities and infrastructure including taxiways, aprons,
aircraft stands, a passenger concourse, an expanded Terminal 2, all related
airside and landside works and associated ancillary and supporting facilities.
The submarine aviation fuel pipelines and submarine power cables also require
diversion as part of the works.
Construction
of the Project is to proceed in the general order of diversion of the submarine
aviation fuel pipelines, diversion of the submarine power cables, land
formation, and construction of infrastructure, followed by construction of
superstructures.
The summary of construction works programme can be referred to
the corresponding Monthly EM&A Reports. Description of relevant contracts
in the reporting period was presented in Appendix A of the Construction Phase
Monthly EM&A Report No. 94.
This
is the 37th Construction Phase Quarterly EM&A Report for the
Project which summarises the key findings of the EM&A programme during the
reporting period from 1 January 2025 to 31 March 2025.
The
Project’s organisation structure is provided in Appendix A. Contact details of the
key personnel have been updated and provided in Table
1.1.
Table 1.1: Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project
Manager’s Representative |
Principal
Manager, Environmental Compliance, Sustainability |
Lawrence
Tsui |
2183
2734 |
(Airport
Authority Hong Kong) |
Environmental
Team Leader |
Terence
Kong |
2828
5919 |
Deputy
Environmental Team Leaders |
Heidi
Yu |
2828
5704 |
|
Ken
Wong |
2828
5817 |
||
Independent
Environmental Checker (IEC) (AECOM
Asia Company Limited) |
Independent
Environmental Checker |
Roy
Man |
3729
0380 |
Deputy
Independent Environmental Checker |
Jackel
Law |
3856
5312 |
Reclamation
Works:
Party |
Position |
Name |
Telephone |
Contract 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture) |
Project Manager |
Alan Mong |
3763 1352 |
Environmental Officer |
Zhang Bin Wang |
3763 1525 |
Airfield Works:
Party |
Position |
Name |
Telephone |
Contract 3305 Airfield Ground Lighting System (ADB Safegate Hong Kong Limited) |
Project Manager |
Allam Al-Turk |
2944 9725 |
Environmental Officer |
Ivan Ting |
9222 9490 |
|
Contract 3306 Observation Facility Control System Supporting
Interim 2RS and 3RS (Chinney Alliance Engineering Limited) |
Project Director |
Dennis Yam |
9551 9920 |
Environmental Officer |
Richard Liu |
9216 8990 |
|
Contract 3308 Foreign Object Debris Detection System (DAS Aviation Services Group) |
Project Manager |
Jeffrey Yau |
9873 7422 |
Contract 3310 North Runway Modification Works (China State Construction Engineering (Hong Kong)
Ltd.) |
Project Manager |
Kingsley Chiang |
9424 8437 |
Environmental Officer |
Federick Wong |
9842 2703 |
Terminal 2 Concourse and Apron Works:
Party |
Position |
Name |
Telephone |
Contract 3402 New Integrated Airport Centres Enabling Works (Wing Hing Construction Co., Ltd.) |
Project Manager |
Wyman Lau |
6112 9753 |
Health Safety Environmental Manager |
Mike Leung |
6625 2550 |
|
Contract 3404 Integrated Airport Control System (Shun Hing Systems Integration Co., Ltd.) |
Project Manager |
Andy Ng |
9102 2739 |
Environmental Officer |
Michael Lo |
6228 3926 |
|
Contract 3405 Third Runway Concourse Foundation and Substructure
Works (China Road and Bridge Corporation – Bachy Soletanche
Group Limited – LT Sambo Co., Ltd. Joint Venture) |
Project Manager |
Francis Choi |
9423 3469 |
Environmental Officer |
Jacky Lai |
9028 8975 |
|
Contract 3408 Third Runway Concourse and Apron Works (Beijing Urban Construction Group Company Limited and
Chevalier (Construction) Company Limited Joint Venture) |
Senior HSE Manager |
Qian Zhang |
5377 7976 |
Environmental Officer |
Ivan Mak |
9422 4805 |
Terminal 2
Expansion:
Party |
Position |
Name |
Telephone |
Contract 3508 Terminal 2 Expansion Works (Gammon Engineering & Construction Company
Limited) |
Project Director |
Richard Ellis |
6201 5637 |
Environmental Officer |
Carrie Kwan |
9276 0551 |
Automated People Mover and Baggage Handling System:
Party |
Position |
Name |
Telephone |
New
Automated People Mover System (TRC Line) (CRRC
Puzhen Bombardier Transportation Systems Limited and CRRC Nanjing Puzhen Co.,
Ltd. Joint Venture) |
Project
Manager |
Hongdan
Wei |
158
6180 9450 |
Environmental
Officer |
H
Y Yue |
9185
8186 |
|
Contract
3602 Existing
APM System Modification Works (Ndsiiigata Transys Co., Ltd.) |
Project
Manager |
Xia
Bo |
6586
4950 |
Environental
Officer |
Y
M Tong |
5316
9801 |
|
Contract
3603 3RS
Baggage Handling System (VISH
Consortium) |
Project
Manager |
K
C Ho |
9272
9626 |
Environmental
Officer |
Richard
Ng |
9802
9577 |
Airport Support
Infrastructure:
Party |
Position |
Name |
Telephone |
Contract 3801 APM and BHS Tunnels on Existing Airport Island (China State Construction Engineering (Hong Kong) Ltd.) |
Project Manager |
Kingsley Chiang |
9424 8437 |
Environmental Officer |
Eunice Kwok |
9243 1331 |
|
Contract 3802 APM and BHS Tunnels and Related Works (Gammon Engineering & Construction Company Limited) |
Project Director |
John Adams |
6111 6989 |
Environmental Officer |
Yan Ng |
5345 8555 |
|
Contract 3804 East and Landside Fire Stations (Beijing Urban Construction Group Company Limited - Beijing
Urban Construction International Company Limited - Kin Shing (Leung's) General Contractors Ltd Joint Venture) |
Project Manager |
Zhang Jinyuan |
6708 0506 |
Environmental Representative |
Karis Lam |
6084 9745 |
|
Contract 3805 New Airport District Police Operational Base (Chinney Construction Co., Ltd.) |
Project Manager |
Peter Li |
9628 0768 |
Environmental Officer |
Mike Li |
6306 8547 |
Construction Support:
Party |
Position |
Name |
Telephone |
Contract 3721 Construction Support Infrastructure
Works (China State Construction
Engineering (Hong Kong) Ltd.) |
Senior Project Manager |
Thomas Lui |
9011 5340 |
Environmental Officer |
John Mak |
6273 8703 |
|
Contract 3728 Minor Site Works (Shun Yuen Construction Company
Limited) |
Contract Manager |
C K Liu |
9194 8739 |
Environmental Officer |
Dan Leung |
6856 5899 |
|
Contract 3733 Emergency Repair Service (Wing Hing Construction Co., Ltd.) |
Project Manager |
Michael Kan |
9206 0550 |
Safety Health Environmental Manager |
Mike Leung |
6625 2550 |
|
Contract 3901A Concrete Batching Facility (K. Wah Concrete Company Limited) |
Project Manager |
Benedict Wong |
9553 2806 |
Environmental Officer |
C P Fung |
9874 2872 |
|
Contract 3901B Concrete Batching Facility (Gammon Construction Limited) |
General Manager |
Gabriel Chan |
2435 3260 |
Environmental Officer |
Rex Wong |
2695 6319 |
|
Contract 3908 Quay Management Services (Gitanes – Crown Asia Joint Venture) |
Project Manager |
Ian Li |
9750 6438 |
Environmental Officer |
Tang Kai Fun |
9406 3526 |
|
Contract 3913 Asphalt Batching Plant (SPR Joint Venture) |
Project Manager |
Xie Yi Sheng |
6580 6005 |
Environmental Officer |
Kenneth Chan |
9300 2182 |
Party |
Position |
Name |
Telephone |
132kV Cable (CLP Power Hong Kong Limited / Kum Shing (K.F.)
Construction Company Limited) |
Engineer |
Ken Fung |
6391 9087 |
Assistant Engineer |
Kevin Wu |
6508 9779 |
The
contact information for the Project is provided in Table
1.2. The public can contact us through the following channels if they
have any queries and comments on the environmental monitoring data and project
related information.
Table 1.2: Contact Information of the Project
Channels |
Contact Information |
Hotline |
3908 0354 |
Email |
env@3rsproject.com |
Fax |
3747 6050 |
Postal Address |
Airport Authority Hong Kong HKIA Tower 1 Sky Plaza Road Hong Kong International Airport Lantau Hong Kong Attn: Environmental Team Leader Mr
Terence Kong c/o Mr Lawrence Tsui (TRD) |
The new North Runway was commissioned in November 2022.
Following the completion of reconfiguration works on the Centre Runway, the 3RS
was commissioned on 28 November 2024.
The key activities of
the Project carried out in the reporting period are located in reclamation
areas and existing airport island respectively. Works in the reclamation areas
included filling
works, pavement works, concourse superstructure works, tunnel works for Automated People Mover (APM)
and Baggage Handling System (BHS) and associated works. Meanwhile, works on the
existing airport island involved Terminal 2 (T2) expansion works, modification
and tunnel works for APM and BHS, utilities works, road and drainage works,
excavation works and 132kV cable laying works. The locations of the key
construction activities after commissioning of 3RS are presented in Figure 1.1.
The
status for all environmental aspects is presented in Table
1.3. The EM&A requirements remained unchanged during the reporting
period.
Table 1.3: Summary of Status for All Environmental Aspects under the Updated EM&A Manual
Parameters |
EM&A Requirements |
Status |
Air Quality |
||
Baseline Monitoring |
At least 14 consecutive days
before commencement of construction work |
The baseline air quality monitoring
result was reported in Baseline Monitoring Report and submitted to EPD under
EP Condition 3.4. |
Impact Monitoring |
At least 3 times every 6 days |
On-going |
Noise |
||
Baseline Monitoring |
Daily for a period of at least two
weeks prior to the commencement of construction works |
The baseline noise monitoring
result was reported in Baseline Monitoring Report and submitted to EPD under
EP Condition 3.4. |
Impact Monitoring |
Weekly |
On-going |
Water Quality |
||
General Baseline Water Quality
Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood
and mid-ebb tides, for at least four weeks prior to the commencement of
marine works. |
The baseline water quality
monitoring result was reported in Baseline Water Quality Monitoring Report
and submitted to EPD under EP Condition 3.4. |
General Impact Water Quality
Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood
and mid-ebb tides. |
General impact water quality
monitoring for water jetting works was completed on 23 May 2017. The general impact water quality
monitoring was terminated after 31 October 2023. |
Initial Intensive Deep Cement
Mixing (DCM) Water Quality Monitoring |
At least four weeks |
The Initial Intensive DCM
Monitoring Report was submitted and approved by EPD in accordance with the
Detailed Plan on DCM. |
Regular DCM Water Quality
Monitoring |
Three times per week until
completion of DCM works. |
Due to the completion of all
marine-based DCM works within April 2022, regular DCM monitoring was ceased
at all monitoring stations starting from 28 April 2022. |
Post-construction
Phase Water Quality Monitoring |
Three
days per week, at mid-flood and mid-ebb tides for four weeks |
The
four-week post-construction phase water quality monitoring exercise was
commenced on 14 November 2023 and completed on 9 December 2023. |
Sewerage and Sewage Treatment |
||
Methodology for carrying out
annual sewage flow monitoring for concerned gravity sewer |
Methodology to be prepared and
submitted to EPD one year before the scheduled commencement of operation of
the proposed third runway. |
The proposed methodology of the
annual sewage flow monitoring was approved by EPD. The annual flow monitoring
was started from June 2021 and completed in 2022. |
Details of the routine H2S
monitoring system for the sewerage system of 3RS |
Details to be prepared and
submitted to EPD at least one year before commencement of the operation of
3RS. |
The H2S monitoring was
started after the commissioning of 3RS on 28 November 2024. |
Waste Management |
||
Waste Monitoring |
At least weekly |
On-going |
Land Contamination |
||
Supplementary Contamination
Assessment Plan (CAP) |
At least 3 months before
commencement of any soil remediation works. |
The Supplementary CAP was
submitted and approved by EPD under EP condition 2.20. |
Site Re-appraisal Summary Report
for Fire Training Facility |
Site Re-appraisal Summary Report
for Fire Training Facility |
Site Re-appraisal Summary Report
for Fire Training Facility was submitted and accepted by EPD. |
Contamination Assessment Report
(CAR) for Golf Course |
CAR to be submitted for golf
course |
The CAR for Golf Course was
submitted and accepted by EPD. |
CAR for Terminal 2 Emergency Power
Supply System |
CAR to be submitted for Terminal 2
Emergency Power Supply Systems |
The CARs for Terminal 2 Emergency
Power Supply Systems were submitted and accepted by EPD. |
Terrestrial Ecology |
||
Pre-construction Egretry Survey
Plan |
Once per month in the breeding
season between April and July, prior to the commencement of Horizontal
Directional Drilling (HDD) drilling works. |
The Egretry Survey Plan was
submitted and approved by EPD under EP Condition 2.14. |
Ecological Monitoring |
Monthly monitoring during the HDD
construction works period from August to March. |
The terrestrial ecological
monitoring at Sheung Sha Chau was completed in January 2019. |
Marine Ecology |
||
Pre-Construction Phase Coral Dive
Survey |
Prior to marine construction works |
The Coral Translocation Plan was
submitted and approved by EPD under EP Condition 2.12. |
Coral Translocation |
- |
The coral translocation was
completed on 5 January 2017. |
Post-translocation Monitoring |
As per an enhanced monitoring
programme based on the Coral Translocation Plan |
The post-translocation monitoring
programme according to the Coral Translocation Plan was completed in April
2018. |
Chinese White Dolphins (CWD) |
||
Baseline Monitoring |
6 months of baseline
surveys before the commencement of land formation related construction works. Vessel line transect
surveys: Two full surveys per month; Land-based
theodolite tracking surveys: Two days per month at the Sha Chau station and
two days per month at the Lung Kwu Chau station; and Passive Acoustic
Monitoring (PAM): For the whole duration of baseline period. |
Baseline CWD results
were reported in the CWD Baseline Monitoring Report and submitted to EPD in
accordance with EP Condition 3.4. |
Impact Monitoring |
Vessel line transect
surveys: Two full surveys per month; Land-based
theodolite tracking surveys: One day per month at the Sha Chau station and
one day per month at the Lung Kwu Chau station; and PAM: For the whole
duration for land formation related construction works. |
The construction
phase CWD monitoring was completed in December 2023. |
Post-construction
Phase Monitoring |
12 months of
post-construction phase CWD monitoring upon the completion of marine
construction works; and Vessel line transect
surveys: Two full surveys per month. |
The
post-construction phase monitoring was completed in December 2024. |
Operation Phase
Monitoring |
12 months of
operation phase CWD monitoring upon full implementation of North Lantau
Marine Park; and Vessel line transect
surveys: Two full surveys per month. |
The operation phase
CWD monitoring was commenced in January 2025. |
Operation Phase
Audit |
SkyPier High Speed
Ferries (HSF) implementation measures: Once every three months for a period
of one year upon operation of 3RS. Spill Response Plan
implementation measures: Once every 6 months for a period of one year upon
operation of 3RS. |
The 1st
audit was conducted in February 2025. The 2nd audit would be
conducted in May 2025. The 1st audit would be conducted
in May 2025. |
Landscape and Visual |
||
Landscape and
Visual Plan |
At least 3 months
before the commencement of construction works on the formed land of the
Project. |
The Landscape
& Visual Plan was submitted and approved by EPD under EP Condition 2.18 |
Baseline
Monitoring |
One-off survey
within the Project site boundary prior to commencement of any construction
works |
The baseline
landscape & visual monitoring result was reported in Baseline Monitoring
Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
Weekly |
On-going |
Establishment
Works Monitoring |
Bi-monthly |
On-going |
Long Term
Management (10 years) Monitoring |
Annually |
On-going |
Environmental Auditing |
||
Regular site
inspection |
Weekly |
On-going |
Marine Mammal
Watching Plan (MMWP) implementation measures |
Monitor and check |
No Marine Mammal
Watching Plan (MMWP) implementation measures was conducted during this
reporting period. |
Dolphin Exclusion
Zone (DEZ) Plan implementation measures |
Monitor and check |
No Dolphin
Exclusion Zone (DEZ) monitoring was conducted during this reporting period. |
SkyPier High
Speed Ferries (HSF) implementation measures |
Monitor and check |
On-going |
Construction and
Associated Vessels implementation measures |
Monitor and check |
On-going |
Silt Curtain
Deployment Plan implementation measures |
Monitor and check |
No Silt Curtain
Deployment Plan measure was implemented at C7a after 17 March 2025. |
Spill Response
Plan implementation measures |
Monitor and check |
On-going |
Complaint Hotline
and Email Channel |
Construction
phase |
On-going |
Environmental Log
Book |
Construction
phase |
On-going |
Taking
into account the construction works in the reporting period, impact monitoring
of air quality, noise, waste management and landscape & visual were carried
out in the reporting period.
The
EM&A programme also involved weekly site inspections and related auditing
conducted by ET for the checking of implementation of required environmental
mitigation measures recommended in the approved EIA Report. To promote the
environmental awareness and enhance the environmental performance of the
contractors, regular environmental management meetings were conducted during
the reporting period which are summarised as below:
·
Thirty-seven environmental management meetings for EM&A review with
works contracts.
The
EM&A programme has been following the recommendations presented in the
approved EIA Report and the Manual. A summary of implementation status of the
environmental mitigation measures for the construction phase of the Project
during the reporting period is provided in Appendix B.
Impact
1-hour Total Suspended Particulates (TSP) monitoring was conducted three times
every six days at two representative monitoring stations during the reporting
period. The locations of monitoring stations are described in Table 2.1 and presented in Figure 2.1.
The
Action and Limit Levels of the air quality monitoring stipulated in the
EM&A programme for triggering the relevant investigation and follow-up
procedures under the programme are provided in Table 2.1
for reference.
Table 2.1: Impact Air Quality Monitoring Stations
Monitoring
Station |
Location |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
AR1A |
Man
Tung Road Park |
306 |
500 |
AR2 |
Village
House at Tin Sum |
298 |
The air
quality monitoring results in the reporting period are summarised in Table 2.2 and the graphical plot is presented in Appendix C.
Table 2.2: Percentage of Air Quality Monitoring Results within Action and Limit Levels
|
AR1A |
AR2 |
Jan 2025 |
100% |
100% |
Feb 2025 |
100% |
100% |
Mar 2025 |
100% |
100% |
Overall |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
All monitoring results were within their corresponding
Action and Limit Levels at all monitoring stations in the reporting period.
General meteorological conditions in the last month of the
previous quarter and this reporting period were recorded and summarised in Table 2.3.
Table 2.3: General Meteorological Condition during Impact Air Quality Monitoring
|
Weather |
Dominant Wind
Direction |
Dec 2024 |
Sunny to Cloudy |
Northwest to
Southeast |
Jan 2025 |
Sunny to Cloudy |
Northeast to
Northwest |
Feb 2025 |
Sunny to Cloudy |
North to
Southwest |
Mar 2025 |
Sunny to Cloudy |
Southwest to
Northwest |
No dust
emission source was observed at the monitoring stations during the monitoring
sessions. As the sensitive receivers were far away from the construction
activities, with the implementation of dust control measures, there was no
adverse impact at the sensitive receivers attributable to the works of the
Project.
Impact
noise monitoring was conducted at four representative monitoring stations once
per week during 0700 and 1900 in the reporting period. The locations of
monitoring stations are described in Table 2.4
and presented in Figure 2.1.
The
Action and Limit Levels of the noise monitoring stipulated in the EM&A
programme for triggering the relevant investigation and follow-up procedures
under the programme are provided in Table 2.4
for reference.
Table
2.4: Impact Noise Monitoring Stations
Monitoring Station |
Location |
Action Level |
Limit Level |
NM1A |
Man Tung Road Park |
When one documented complaint is received from any one of
the sensitive receivers |
75 dB(A) |
NM4 |
Ching Chung Hau Po Woon Primary School |
65dB(A) / 70 dB(A) (i) |
|
NM5 |
Village House in Tin Sum |
75 dB(A) |
|
NM6 |
House No. 1, Sha Lo Wan |
75 dB(A) |
Note: (i) The Limit Level for NM4 is reduced to 70 dB(A) for being an educational institution. During school examination period, the Limit Level is further reduced to 65 dB(A). |
The noise monitoring results in the
reporting period are summarised in Table 2.5 and
the graphical plot is presented in Appendix
C.
Table
2.5: Percentage of Noise Monitoring Results within Action and Limit Levels
|
NM1A |
NM4 |
NM5 |
NM6 |
Jan 2025 |
100% |
100% |
100% |
100% |
Feb 2025 |
100% |
100% |
100% |
100% |
Mar 2025 |
100% |
100% |
100% |
100% |
Overall |
100% |
100% |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
No complaints
were received from any sensitive receiver that triggered the Action Level.
General
meteorological conditions in the last month of the previous quarter and this
reporting period were recorded and summarised in Table
2.6.
Table 2.6: General Meteorological Condition during Impact Noise Monitoring
|
Weather |
Dec 2024 |
Sunny to Cloudy |
Jan 2025 |
Sunny to Cloudy |
Feb 2025 |
Sunny to Cloudy |
Mar 2025 |
Sunny to Cloudy |
Major
sources of noise dominating the monitoring stations observed during the
construction noise impact monitoring were traffic noise near NM1A, school
activities near NM4, and aircraft noise near NM6. As the sensitive receivers
were far away from the construction activities, with the implementation of
noise control measures, there was no adverse impact at the sensitive receivers
attributable to the works of the Project.
All
water impact monitoring and post-construction phase water quality monitoring
have been completed, with results presented in the Annual EM&A Report for
2023. The analysis in the report
indicates that the post-construction phase water quality monitoring did not
reveal significant changes compared to the baseline levels. Therefore, it
can be concluded that the marine works of the Project during construction phase
did not cause deterioration in or adverse impacts on the marine water quality
surrounding the Project site.
In
accordance with the Manual, waste generated from construction activities was
audited once per week to determine if wastes were being managed in accordance
with the Waste Management Plan (WMP) prepared for the Project,
contract-specific WMP, and any statutory and contractual requirements. All
aspects of waste management including waste generation, storage,
transportation, and disposal were assessed during the audits.
The Action and Limit Levels of the construction waste are
provided in Table 2.7.
Table 2.7: Action and Limit Levels for Construction Waste
Monitoring Stations |
Action Level |
Limit Level |
Construction Area |
When one valid
documented complaint is received |
Non-compliance of
the WMP, contract-specific WMPs, any statutory and contractual requirements |
Weekly
monitoring of the Project construction works was carried out by the ET in the
reporting period to check and monitor the implementation of proper waste
management practices.
Recommendations
made by the ET included provision and maintenance of proper chemical waste
storage area, as well as handling, segregation, and regular disposal of general
refuse. The contractors took actions to implement the recommended measures.
Waste management audits were carried out by ET according to the requirements of
the Waste Management Plan, updated EM&A Manual and the implementation
schedule of the waste management mitigation measures in Appendix B.
Based
on updated contractors’ information, summary of construction waste generated in
the reporting period is presented in Table 2.8.
The ET and IEC carried out site audits regularly and reviewed the trip ticket
system.
Table 2.8: Construction Waste Statistics
|
C&D(1)
Material Stockpiled for Reuse or Recycle (m3) |
C&D Material
Reused in the Project (m3) |
C&D Material Reused
in other Projects (m3) |
C&D Material
Transferred to Public Fill(2) (m3) |
Chemical Waste (kg) |
Chemical Waste (l) |
General Refuse (tonne) |
Previous
reporting period |
|||||||
Oct
2024 |
293 |
14,738 |
0 |
7,395 |
0 |
2,400 |
5,959 |
Nov
2024 |
833 |
0 |
0 |
4,533 |
1,890 |
2,600 |
5,907 |
Dec
2024(3) |
353 |
0 |
0 |
6,284 |
800 |
0 |
7,893 |
Total |
1,479 |
14,738 |
0 |
18,212 |
2,690 |
5,000 |
19,759 |
This
reporting period |
|||||||
Jan
2025 |
1,583 |
160 |
0 |
8,037 |
0 |
0 |
4,472 |
Feb
2025 |
8 |
11,494 |
0 |
7,826 |
350 |
0 |
2,959 |
Mar
2025 (3) |
0 |
1,334 |
0 |
6,218 |
300 |
0 |
4,520 |
Total |
1,591 |
12,988 |
0 |
22,081 |
650 |
0 |
11,951 |
Notes:
(1) C&D refers to
Construction and Demolition.
(2) C&D materials not suitable
for reuse on-site, including asphalt waste and sediment slurry, were
transferred to public fill during the reporting period.
(3) Updated figures were
provided by contractors.
There was no complaint, non-compliance of the WMP,
contract-specific WMPs, statutory and contractual requirements that triggered
Action and Limit Levels in this reporting period.
Marine sediment is managed according to the EIA Report,
Updated EM&A Manual and Waste Management Plan and the proposal of Further
Development on Treatment Level / Details and the Reuse Mode for Marine Sediment
(hereinafter referred to as “Further Development Proposal”) of the Project. The
storage conditions of the excavated marine sediment, treatment process, final
backfilling location as well as associated records were inspected and checked
by ET and verified by IEC to ensure they were in compliance with the
requirements as stipulated in the Waste Management Plan and Further Development
Proposal.
Backfilling works for treated marine
sediment generated from the reclaimed land area were conducted during the
reporting period. The details of the marine sediment sampling, treatment and
backfilling can be referred to Annual EM&A Report No.8.
The operation phase CWD
monitoring was conducted by vessel line transect survey at a frequency of two
full surveys per month since January 2025. The vessel survey transects followed
the transect lines proposed in the Manual and are consistent with those used in
the Agriculture, Fisheries and Conservation Department (AFCD) long-term CWD
monitoring programme. The transect locations of CWD monitoring by vessel line
transect survey are shown in Figure
2.2.
Survey
Effort
During the reporting period from
January to March 2025, a total of six sets of vessel line transect survey
covering all transects in Northeast Lantau (NEL), Northwest Lantau (NWL), Airport
West (AW), West Lantau (WL)
and Southwest Lantau
(SWL) survey areas were conducted at a frequency of twice per month, in each
survey area.
A total of around 1,331 km of survey
effort was collected from these surveys, with around 96.6% of the total survey
effort being conducted under favourable weather condition (i.e. Beaufort Sea
State 3 or below with favourable visibility). Details of the survey effort data
are presented in Appendix C.
CWD
Sighting
From January to March 2025, there
were a total of 53 sightings of CWD, with 110 dolphins sighted (Table 2.9). All these sightings were recorded during on-effort
searches under favourable weather condition.
When breaking down the sightings by
survey areas, 37 sightings with a total of 83 dolphins and eight sightings with
a total of 10 dolphins were recorded in WL and SWL respectively during the
current reporting period. Six sightings of 13 dolphins were recorded in NWL
while two sighting of four dolphins were recorded in the Airport West water
within the NWL survey area. No CWD was sighted in NEL survey area.
Compared with the previous quarter
(i.e. October to December 2024), the total number of CWD sightings and the
total number of the dolphins have increased by 130% and 96% respectively. There
was a notable increase in both dolphin sightings and the number of dolphins in
both WL and NWL survey area in the current reporting quarter.
Compared with the same quarter of
last year (i.e., January to March 2024), there was also an increase in both the
total number of sightings and the total number of dolphins by 152% and 47%
respectively. In WL, there was an increase in both the number of sightings and
number of dolphins by 105% and 22% respectively. In SWL, there was a slight
increase in both number of sightings and number of dolphins. Moreover, there
were significant increases in both total number of sightings and total number
of dolphins in NWL as there was no sighting in the same reporting period in
2024.
Table 2.9 below shows the comparison of the
numbers of sightings and dolphins amongst the current reporting period, last
quarter, and the same quarter of last year.
Table
2.9: Summary of Number of CWD Sightings and Number of Dolphins for the Same
Quarter Last Year, Previous Quarter, and Current Reporting Period
|
Same
Quarter of Last Year January to March 2024 |
Previous
Reporting Period October to December 2024 |
Current
Reporting Period January to March 2025 |
NEL |
0 (0) |
0 (0) |
0 (0) |
NWL |
0 (0) |
2 (3) |
6 (13) |
AW |
1 (1) |
0 (0) |
2 (4) |
WL |
18 (68) |
11 (23) |
37 (83) |
SWL |
2 (6) |
10 (30) |
8 (10) |
Total |
21 (75) |
23 (56) |
53 (110) |
Note: Values in ( ) represent number
of dolphins
The distribution of CWD sightings
recorded from January to March 2025 is illustrated in Figure
2.3. In NWL, most of the CWD sightings were clustered at the western
water of HKIA while another two sightings were recorded in the western water of
Sha Chau and the northern water outside of SCLKCMP respectively. In WL, CWD
sightings were scattered throughout the waters between Tai O and Fan Lau. In
SWL, the CWD sightings were recorded in water near Fan Lau and Tai Long Wan as
well as at the northern water of Soko’s Island. No CWD sighting was recorded in
NEL survey area during the reporting period. Details of the sighting data are
presented in Appendix C.
Figure
2.3: Sightings Distribution of Chinese White Dolphins from January to March
2025
Remarks: (1) Please note that there are 53 pink circles on the map
indicating the sighting locations of CWD. Some of them were very close to each other
and therefore appear overlapped on this sighting distribution map. (2) Marine
Park excludes land area and the landward boundary generally follows the high
water mark along the coastline.
Group Size
From January
to March 2025, the group size of CWD sightings ranged from one to eight
dolphins. The average group size of CWD was 2.08 dolphins per group, which is
smaller than that of the last quarter (2.43 dolphins per group). The average
group size of CWD in this reporting quarter is also smaller than that of the
same quarter of last year (3.57 dolphins per group).
In this reporting quarter, majority
of the CWD sightings were in small group size (i.e., 1-2 dolphins). There was
no CWD sighting with large group size (i.e., 10 or more dolphins) during this
reporting period.
There was no apparent pattern in the
distribution of small-sized dolphin groups, medium-sized dolphin groups and
large-sized dolphin groups in all survey areas. Sighting locations of CWD
groups with different group sizes are depicted in Figure
2.4.
Figure 2.4: Sighting Locations of Chinese White
Dolphins with Different Group Sizes
Remarks: (1) Please note that there are
53 circles on the map indicating the sighting locations of CWD. Some of them
were very close to each other and therefore appear overlapped on this sighting
distribution map. (2) Marine park excludes land area and the landward boundary
generally follows the high water mark along the coastline.
Activities
and Association with Fishing Boats
From January to March 2025, 12
sightings of CWD were recorded with foraging activities. Amongst them, three
sightings were observed associated with operating gillnetter and one sighting
with operating purse seiner in WL.
Sightings with foraging activities
recorded in the current reporting period was higher than that in the previous
reporting period (i.e., six sightings involved foraging activities between
October and December 2024). The number of CWD sightings with foraging
activities in this reporting period was also higher than that in the same
quarter of last year (i.e., six sightings between January to March 2024).
The sighting locations of CWDs
engaged in different behaviours during the current reporting period are illustrated in Figure 2.5.
Figure 2.5: Sighting Locations of Chinese White Dolphins Engaged
in Different Behaviours
Remarks: (1) Marine park excludes land area and the landward boundary generally
follows the high water mark along the coastline.
Mother-calf Pairs
From January to March 2025, four
sightings of CWD were recorded with the presence of mother-and-unspotted
juvenile pairs and/or mother-and-calf pair, which was more than that recorded
in the previous reporting quarter (i.e., two sightings between October to
December 2024). Yet, the
number of CWD sightings with the presence of mother-calf pairs was less than
that recorded in the same quarter of last year (i.e., seven sightings between
January to March 2024).
These four sightings with the
presence of mother-calf pairs recording during the reporting period were
recorded in WL and SWL survey area. The locations of CWD sightings with the
presence of mother-calf pairs are shown in Figure 2.6.
Figure 2.6: Sighting
Locations of Mother-calf Pairs
Remarks:
(1) Please note that there are four circles on the map indicating the sighting
locations of CWD. Some of them were very close to each other and therefore
appear overlapped on this sighting distribution map.
(2)
Marine park excludes land area and the landward boundary generally follows the
high water mark along the coastline.
Photo Identification
Between
January and March 2025, a total number of 36 different CWD individuals were
identified altogether for a total of 61 times. Re-sighting information of CWD
individuals provides an initial idea of their range use and apparent connection
between different areas of Lantau waters. Amongst these 36 different CWD
individuals, 13 animals (i.e., NLMM023, SLMM003, SLMM007, SLMM014, SLMM023,
SLMM031, SLMM073, WLMM043, WLMM056, WLMM079, WLMM080, WLMM114 and WLMM147) were
sighted for more than once. The most frequently re-sighted individual of this
quarter is WLMM056 which has been re-sighted 5 times followed by SLMM003 and
SLMM023 both being re-sighted for 4 times.
Four
individuals namely SLMM014, WLMM056, WLMM079 and WLMM114 were re-sighted in
different survey areas during this reporting period. The numbers of CWD
individuals re-sighted more than once was higher than that of the last report
reporting period from October to December 2024 and the number of identified
individuals showed cross-area movement is showing
the same trend (i.e. Four CWD
individuals in current reporting period versus only one in last reporting
period).
A summary of photo identification works is presented
in Table 2.10. Representative photos of the 36
identified individuals
and figures depicting
the sighting locations of the aforementioned four individuals re-sighted in
different survey areas in this reporting period are presented in Appendix C.
Table 2.10: Summary of Photo
Identification
Individual
ID |
Date
of sighting |
Sighting
Group No. |
Area |
|
Individual
ID |
Date
of sighting |
Sighting
Group No. |
Area |
NLMM013 |
20-Jan-25 |
1 |
AW |
|
WLMM001 |
20-Mar-25 |
5 |
WL |
NLMM023 |
19-Feb-25 |
3 |
NWL |
|
WLMM004 |
18-Feb-25 |
6 |
WL |
19-Mar-25 |
1 |
NWL |
|
WLMM007 |
20-Jan-25 |
6 |
WL |
|
NLMM027 |
19-Feb-25 |
3 |
NWL |
|
WLMM029 |
21-Mar-25 |
4 |
WL |
NLMM055 |
20-Mar-25 |
5 |
WL |
|
WLMM043 |
20-Jan-25 |
1 |
AW |
NLMM063 |
19-Feb-25 |
3 |
NWL |
|
19-Feb-25 |
1 |
NWL |
|
NLMM065 |
19-Feb-25 |
3 |
NWL |
|
2 |
NWL |
||
NLMM094 |
19-Mar-25 |
1 |
NWL |
|
WLMM049 |
20-Mar-25 |
5 |
WL |
SLMM003 |
20-Mar-25 |
4 |
WL |
|
WLMM056 |
17-Jan-25 |
5 |
SWL |
5 |
WL |
|
20-Jan-25 |
9 |
WL |
|||
7 |
WL |
|
12-Mar-25 |
10 |
SWL |
|||
21-Mar-25 |
5 |
WL |
|
21-Mar-25 |
1 |
WL |
||
SLMM007 |
20-Mar-25 |
1 |
WL |
|
3 |
WL |
||
2 |
WL |
|
WLMM063 |
20-Jan-25 |
2 |
WL |
||
21-Mar-25 |
2 |
WL |
|
WLMM079 |
3-Jan-25 |
1 |
SWL |
|
SLMM014 |
12-Feb-25 |
8 |
SWL |
|
20-Mar-25 |
1 |
WL |
|
20-Mar-25 |
5 |
WL |
|
21-Mar-25 |
5 |
WL |
||
SLMM023 |
18-Feb-25 |
3 |
WL |
|
WLMM080 |
18-Feb-25 |
5 |
WL |
20-Mar-25 |
5 |
WL |
|
20-Mar-25 |
6 |
WL |
||
21-Mar-25 |
1 |
WL |
|
WLMM114 |
20-Jan-25 |
9 |
WL |
|
5 |
WL |
|
3-Mar-25 |
11 |
SWL |
|||
SLMM030 |
5-Feb-25 |
1 |
NWL |
|
WLMM118 |
18-Feb-25 |
5 |
WL |
SLMM031 |
20-Mar-25 |
7 |
WL |
|
WLMM147 |
20-Mar-25 |
1 |
WL |
8 |
WL |
|
21-Mar-25 |
5 |
WL |
|||
21-Mar-25 |
4 |
WL |
|
WLMM180 |
20-Jan-25 |
5 |
WL |
|
SLMM035 |
21-Mar-25 |
4 |
WL |
|
WLMM204 |
11-Feb-25 |
1 |
WL |
SLMM052 |
20-Mar-25 |
5 |
WL |
|
WLMM205 |
11-Feb-25 |
1 |
WL |
SLMM071 |
5-Feb-25 |
1 |
NWL |
|
WLMM206 |
11-Feb-25 |
2 |
WL |
SLMM073 |
20-Mar-25 |
1 |
WL |
|
WLMM207 |
11-Feb-25 |
2 |
WL |
2 |
WL |
|
WLMM208 |
11-Feb-25 |
2 |
WL |
||
21-Mar-25 |
2 |
WL |
|
|
|
|
|
During the reporting period, no dolphin observation
station was deployed by the contractor for continuous monitoring of the DEZ in
accordance with the DEZ Plan. During this
reporting period, no training session were provided by the ET for the proposed
dolphin observers.
The construction
vessel management are presented in Section 2.8 below.
According
to Section 10.6.2.2 of the Updated EM&A Manual, audits of HSF
implementation measures and Spill Responses Plan implementation measures will
be conducted once every three months and every six months respectively for one
year upon operation of 3RS. The first audit of HSF implementation measures was
conducted in February 2025. During the audit period from 28 November 2024 to 28
February 2025, all the HSFs complied with the HSF Plan. The second audit of HSF
implementation measures will be conducted in May 2025. The first audit of the
Spill Responses Plan measures will be conducted in May 2025.
Site inspections of the construction works to audit the
implementation of proper environmental pollution control and mitigation
measures for the Project were conducted by ET and IEC on a weekly and bi-weekly
basis, respectively. Besides, ad-hoc site inspections were also conducted by ET
and IEC if environmental problems were identified, or subsequent to receipt of
an environmental complaint, or as part of the investigation work. These site
inspections provided a direct means to reinforce the specified environmental
protection requirements and pollution control measures in construction sites.
During
site inspections, environmental situation, status of implementation of
pollution control and mitigation measures were observed. Environmental
documents and site records, including waste disposal record, maintenance record
of environmental equipment, and relevant environmental permit and licences,
were also checked on-site. Observations
were recorded in the site inspection checklist and passed to the contractor
together with the appropriate recommended mitigation measures where necessary
in order to advise contractors on environmental improvement, awareness and
on-site enhancement measures. The
observations were made with reference to the following information during the
site inspections:
· The EIA
and EM&A requirements;
· Relevant
environmental protection laws, guidelines, and practice notes;
· The EP
conditions and other submissions under the EP;
· Monitoring
results of EM&A programme;
· Works
progress and programme;
· Proposal
of individual works;
· Contract
specifications on environmental protection; and
· Previous
site inspection results.
Good
site practices were implemented in the project to enhance environmental
performance. Key examples implemented in the Project are highlighted as below:
1. Provision
of wheel washing for construction vehicles before leaving the site area.
2. Provision
of environmental training for site personnel by the contractor.
3. Conducted self-monitoring of an effluent sample from the wastewater treatment facility by the contractor.
|
|
|
Wheel washing at site exit |
Provision of environmental training
for site personnel |
Self-monitoring of effluent sample
from wastewater treatment facility |
Besides, advice was given when necessary to ensure the
construction workforce were familiar with relevant procedures, and to maintain
good environmental performance on site. Regular toolbox talks on environmental
issues were organised for the construction workforce by the contractors to
ensure understanding and proper implementation of environmental protection and
pollution control mitigation measures.
A summary of implementation status of the environmental
mitigation measures for the construction phase of the Project during the
reporting period is provided in Appendix
B.
Implementation of applicable landscape and visual
mitigation measures (reference to the environmental protection measures CM1 –
CM10 and OM7 in Appendix B)
was monitored regularly in
accordance with the Manual. The implementation status of the environmental
protection measures is summarised in Table 2.11. For trees which were managed under the
Project during the reporting period, relevant measures (i.e., CM1 – CM9) were implemented by Contract 3508
and 132kV cable. For CM10, the advanced hydroseeding works around taxiways and
runways were carried out during the reporting period. The total number
of retained trees, transplanted trees and to-be-transplanted trees under the
management of Project are summarized in Table 2.12.
The total number of retained trees of the Project as of
March 2025 was 76. Compared to 24 retained trees reported in the previous
reporting period, the change in number was due to the following reason:
· The works of 132kV cable commenced the maintenance of 52
retained trees.
The cumulative total number of
transplanted trees of the Project remained unchanged (i.e. 26 nos.) comparing
with previous reporting quarter. Details
of the summary of transplanted trees are shown in Table
2.13. Photos of the transplanted trees
are presented in Table 2.14.
For OM7, the bi-monthly site
inspections for 12-month establishment period was undertaken in March 2025
during the reporting period.
Table 2.11: Landscape and Visual – Construction Phase Audit Summary
Landscape
and Visual Mitigation Measures during Construction Implementation Status |
Implementation
Status |
Relevant
Contract(s) in the Reporting Period |
CM1 –
The construction area and contractor’s temporary works areas shall be
minimised to avoid impacts on adjacent landscape. |
The
implementation of mitigation measures were checked by ET during weekly site
inspection and clarified by the Contractors during the monthly Environmental
Management Meetings. Implementation of the measures CM5, CM6 and CM7 by
Contractors was observed. |
All works contracts |
CM2 –
Reduction of construction period to practical minimum. |
||
CM3 –
Phasing of the construction stage to reduce visual impacts during the
construction phase. |
||
CM4 –
Construction traffic (land and sea) including construction plants,
construction vessels and barges shall be kept to a practical minimum. |
||
CM5 –
Erection of decorative mesh screens or construction hoardings around works
areas in visually unobtrusive colours. |
||
CM6 –
Avoidance of excessive height and bulk of site buildings and structures |
||
CM7 –
Control of night-time lighting by hooding all lights and through minimisation
of night working periods |
||
CM8 –
All existing trees shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works areas |
Tree
Protection Specifications were provided in the relevant Contract
Specifications respectively for implementation by the Contractors under the
Project. The Contractors’ performance on the implementation of the trees maintenance and protection measures were observed and checked by the ET weekly during construction period. |
3508, 132kV Cable |
CM9 –
Trees unavoidably affected by the works shall be transplanted where
practical. A detailed Tree
Transplanting Specification shall be provided in the Contract Specification,
if applicable. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme |
Tree
Transplanting Specifications were provided in the relevant Contract
Specifications respectively for implementation by the Contractors under the
Project where trees will unavoidably be affected by the construction works. The
Contractors were required to submit Method Statements for tree transplanting
prior to the transplanting works. Tree inspections were conducted by ET to
check the tree transplanting works implemented by the Contractors on site. The
Contractors’ performance on the implementation of trees maintenance and
protection measures on transplanted trees were observed and checked by the ET
bi-monthly during the 12-month establishment period after the completion of
each batch of transplanting works. Long
term management of the transplanted trees were currently monitored by ET
annually. |
3508 |
CM 10
– Land formation works shall be followed with advanced hydroseeding around
taxiways and runways as soon as practical |
The
Contractor’s performance on the implementation of advanced hydroseeding works
was observed and checked by the ET during the weekly site inspection. |
3310 |
OM7 –
Compensatory tree planting for all felled trees shall be provided to the
satisfaction of relevant Government departments. Required numbers and locations of
compensatory trees shall be determined and agreed separately with Government
during the Tree Felling Application process under the relevant technical
circulars(1) |
Compensatory trees have been planted in
batches at different time periods. The
compensatory trees were checked by ET bi-monthly during the 12-month
establishment period after the completion of each batch of compensatory tree
planting works. Subsequently,
the trees were monitored annually throughout the 10-year long-term management
period, succeeding the establishment period for each batch of compensatory
planting. |
AAHK |
(1) AAHK is the management and maintenance
agency of the compensatory trees. Tree Felling Application is not required for
3RS project.
Table 2.12: Summary of the Number of Retained, Transplanted and To-be-transplanted Trees in the Reporting Period
Contract
No. / Works |
Retained
(nos.) |
Transplanted
(nos.) |
To-be-transplanted
(nos.) |
|
Establishment
Period |
Maintenance
Period |
|||
3503(1) |
0 |
0 |
9 |
0 |
3508 |
24 |
0 |
12 |
0 |
3801(2) |
0 |
0 |
5 |
0 |
132kV Cable |
52 |
0 |
0 |
0 |
Grand Total |
76 |
0 |
26 |
0 |
Notes:
(1)
Contract 3503 was completed
and the 9 transplanted trees, including T835, T836, T838, T812, T814, T815,
T829, T830 and T831, have been handed over to AAHK in February 2022.
(2)
The 5 transplanted trees,
including CT276, CT1253, CT1194, CT1794 and CT1795, have been handed over to
other management agencies. Details of the management agency are presented in Table 2.13.
Table 2.13: Summary of the Transplanted Trees Updated in the Reporting Period
Tree
ID |
Transplant
Date |
Management
Stage |
Management
Agency |
Remarks |
CT276 |
3 May 2018 |
Long Term
Management period Jun 2019 – May 2028 |
Southern Landside
Petrol Filling Station |
Establishment Period
was completed. Next inspection will be conducted in February 2026. Photos of
the last inspection in February 2025 can be referred to Table 7.7 of the
Construction Phase Monthly EM&A Report No. 110. |
CT1253 |
4 May 2018 |
Long Term
Management period Jun 2019 – May 2028 |
Southern Landside
Petrol Filling Station |
|
T835 |
22 Jan 2020 |
Long Term
Management period Feb 2021 – Jan 2030 |
AAHK |
Establishment Period
was completed. The trees within the land parcel was acquired for construction
of infrastructure. The trees were felled in 2023. |
T836 |
13 Dec 2019 |
Long Term
Management period Feb 2021 – Jan 2030 |
AAHK |
|
T838 |
22 Jan 2020 |
Long Term
Management period Feb 2021 – Jan 2030 |
AAHK |
|
T812 |
21 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
Establishment
Period was completed. Next inspection will be conducted in December 2025. Photos
of the last inspection in December 2024 can be referred to Table 7.7 of the
Construction Phase Monthly EM&A Report No. 108. |
T814 |
20 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
|
T815 |
15 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
|
T829 |
18 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
|
T830 |
14 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
|
T831 |
19 Dec 2020 |
Long Term
Management period Jan 2022 – Dec 2031 |
AAHK |
|
T1493 |
6 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
Establishment
Period was completed. Next inspection will be conducted in July 2025. Photos
of the last inspection in July 2024 can be referred to Table 7.7 of the
Construction Phase Monthly EM&A Report No.103. |
T1494 |
6 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1495 |
10 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1496 |
5 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1497 |
5 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1498 |
29 Jun 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1499 |
29 Jun 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1500 |
30 Jun 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1501 |
30 Jun 2021 |
Long Term Management
period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1502 |
5 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1503 |
6 Jul 2021 |
Long Term
Management period Aug 2022 – Jul 2031 |
Contract 3508 |
|
T1504 |
24 Jun 2021 |
Long Term Management
period Aug 2022 – Jul 2031 |
Contract 3508 |
|
CT1194 |
4 May 2018 |
Long Term
Management period Jun 2019 – May 2028 |
Southern Landside
Petrol Filling Station |
Establishment
Period was completed. Uprooted and collapsed due to Typhoon Higos on 18
August 2020. Tree removal was conducted as recommended by tree specialist of
the contractor of Southern Landside Petrol Filing Station. |
CT1794 |
3 May 2018 |
Long Term
Management period Jun 2019 – May 2028 |
AsiaWorld-Expo |
Establishment Period
was completed. The tree within the land parcel was acquired by the government
for construction of emergency hospital to handle COVID19 pandemic at
AsiaWorld-Expo. The tree was felled in late 2020. |
CT1795 |
3 May 2018 |
Long Term
Management period Jun 2019 – May 2028 |
AsiaWorld-Expo |
Establishment
Period was completed. The tree within the land parcel was acquired by the
government for construction of emergency hospital to handle COVID19 pandemic
at AsiaWorld-Expo. The tree was felled in late 2020. |
Table 2.14: Photos of the Existing Transplanted Trees Inspected in the Reporting Period
|
|
CT276 |
CT1253 |
The Supplementary CAP was submitted to EPD pursuant to EP Condition
2.20. The CARs for Golf Course and T2 Emergency Power Supply Systems (EPSS)
were submitted to EPD in accordance with EP Condition 1.9 and the Supplementary
CAP, in which no land contamination issues were identified. EPD has issued no
further comment for aforesaid CARs. No leakage was found after the
removal of underground fuel pipelines and all required additional photos were
submitted to EPD.
According to the approved supplementary CAP, there are 3
remaining locations where site re-appraisal / additional site investigation is
proposed. The site
re-appraisal summary report for Fire Training Facility was submitted and
accepted by EPD on 20 December 2023. The status of site re-appraisal/
additional site investigation of the 2 remaining locations (Fuel Tank Room to the west of CAD Antenna Farm and Airside
Petrol Filling Station) shall be further updated upon latest
development programme is available.
The Marine Travel Routes and Management Plan for High Speed
Ferries of SkyPier (the SkyPier Plan) was submitted to the Advisory Council on
the Environment for comment and subsequently submitted to and approved by EPD
in November 2015 under EP Condition 2.10. The approved SkyPier Plan is
available on the dedicated website of the Project. In the SkyPier Plan, AAHK
has committed to implement the mitigation measure of requiring HSFs of SkyPier
travelling between HKIA and Zhuhai / Macau to start diverting the route with
associated speed control across the area, i.e. Speed Control Zone (SCZ), with
high CWD abundance. The route diversion and speed restriction at the SCZ have
been implemented since 28 December 2015.
According to EP Condition 2.10 and the SkyPier Plan, the
annual daily average limit and the maximum daily movement cap were to be
implemented before the NLMP designation on 1 November 2024. Consequently, the
limit and cap are no longer applicable.
During January 2025, no ferry movement between HKIA SkyPier
and Zhuhai was recorded and a total 6 ferry movements between HKIA
SkyPier and Macau were audited. The average speed of
the HSF travelling through the Speed Control Zone (SCZ) ranged from 11.6 to
13.5 knots. All HSFs travelled through the SCZ with average speed within 15
knots in compliance with the SkyPier Plan.
No ferry movement between HKIA SkyPier and Zhuhai / Macau
was recorded in February and March 2025.
During the previous reporting period, two ferries were
recorded with the speed deviation within the NLMP in December 2024. These two
cases were closed after the ET’s investigation.
The summary of the SkyPier Plan monitoring result is
presented in Graph 1.
Graph 1: Summary of SkyPier High Speed Ferries Monitoring
Results
On the implementation of
the updated Marine Travel Routes and Management Plan for Construction and
Associated Vessels (MTRMP-CAV), the requirements of the NLMP have been included
in the Maritime Surveillance System (MSS). The MSS automatically
recorded deviation cases such as speeding, and entering no entry zone. ET
conducted bi-weekly audit of relevant information
including AIS data, vessel tracks and other relevant records to ensure
sufficient information were provided by the system and the contractors complied
with the requirements of the MTRMP-CAV. The contactors submitted 3-month
rolling vessel plans for construction vessel activities to AAHK in order to
help maintain the number of construction vessels to a practicable minimum. The
IEC also performed audit on the compliance of the requirements as part of the
EM&A programme.
During the reporting period,
deviations including speeding and entering no-entry zones were identified.
After investigation by the contractors’ Construction Traffic Control Centre
(CTCC) representatives, all the concerned captains were reminded to comply with
the requirements of the MTRMP-CAV.
One skipper training workshop was
held with one skipper by ET. One skipper training workshop was held by contractor’s Environmental Officer with one skipper
and competency test was conducted subsequently with the trained skipper by ET.
With
reference to Appendix E of the Manual, it is noted that the key assumptions
adopted in approved EIA report for the construction phase are still valid and
no major changes are involved. The environmental mitigation measures
recommended in the approved EIA Report remain applicable and shall be
implemented in undertaking construction works for the Project.
During
the reporting period, environmental related licenses and permits required for
the construction activities were checked. No non-compliance with environmental
statutory requirements was recorded.
During the reporting period, one
environmental complaint was received and the details are summarized in Table 3.1 below.
Table 3.1: Summary of Environmental Complaints
Date of Complaint
Received |
Details |
Analysis/ Remedial
Actions |
Status |
14 January 2025 |
A complaint regarding
dust nuisance was received. |
A complaint regarding
dust nuisance was received on 14 January 2025. The case was investigated by
ET in accordance with the Manual and the Complaint Management Plan of the
Project. ET requested the relevant contractor to provide information
regarding the complaint and replies indicated cleaning works were carried out
inside the North Wing Level 6 of Terminal 2 Concourse. The relevant
contractor improved their dust mitigation measures by wetting the floor and
using a mist sprayer prior to undertaking the cleaning works; and conducting
refresher training with frontline cleaning workers on dust suppression measures
for cleaning works. During the ET’s site inspections, no dust related item
was recorded. The relevant contractor was reminded to keep review their dust
mitigation measures and to enhance dust suppression measures before
conducting cleaning and other dusty works to prevent dust nuisance. Hence,
the case was considered closed. |
Closed |
Neither
notification of summons nor prosecution was received during the reporting
period.
Cumulative
statistics on valid exceedance, non-compliance, complaints, notifications of
summons and status of prosecutions are summarised in Table
3.2 and Table 3.3.
Table 3.2: Statistics for Valid Exceedances for the Environmental Monitoring
|
|
Total
No. Recorded in the Reporting Period |
Total
No. Recorded since the Project Commenced |
1-hr TSP |
Action Level |
0 |
0 |
Limit Level |
0 |
0 |
|
Noise |
Action Level |
0 |
0 |
Limit Level |
0 |
0 |
|
Waste |
Action Level |
0 |
1 |
Limit Level |
0 |
0 |
|
Water |
Action Level |
Nil(2) |
0 |
Limit Level |
Nil(2) |
0 |
|
CWD |
Action Level |
Nil(3) |
0 |
Limit Level |
Nil(3) |
0 |
Remarks:
1) Non-project related triggers of Action or Limit Level are not shown in this
table.
2) With the completion of land formation works including seawall construction
and all marine filling works in the first quarter of 2023, the construction
phase water quality impact monitoring was terminated after 31 October 2023. No
water quality impact monitoring was undertaken during the reporting period.
3) Construction phase CWD monitoring by small vessel line-transect survey
supplemented by land-based theodolite tracking survey and passive acoustic
monitoring was completed in December 2023. No CWD impact monitoring was
undertaken during the reporting period.
Table 3.3: Statistics for Non-compliance, Complaints, Notifications of Summons and Prosecution
Reporting Period |
Cumulative Statistics |
|||
|
Non-compliance |
Complaints |
Notifications of Summons |
Prosecutions |
This reporting period |
0 |
1 |
0 |
0 |
From 28 December 2015 to end of
the reporting period |
0 |
81 |
2 |
2 |
The new North Runway was commissioned in November 2022.
Following the completion of reconfiguration works on the Centre Runway, the 3RS
was commissioned on 28 November 2024. In the first quarter of 2025, the
EM&A programme has been implemented as planned, including construction air
quality, construction noise, operation phase CWD monitoring, and waste
monitoring, as well as environmental site inspections.
Key project activities included filling, pavement,
concourse superstructure, and tunnel works for AMP and BHS in reclamation
areas, and T2 expansion, utilities, road and drainage works excavation, and
132kV cable laying on the existing airport island.
During
the reporting period, monitoring results showed no exceedances in construction
dust, construction noise, and construction waste and no non-conformity
in landscape & visual monitoring. All water impact monitoring
and post-construction phase water quality monitoring have been completed.
Operation phase CWD monitoring recorded 53 sightings of 110 dolphins under
favorable conditions.
Site inspections were conducted regularly to ensure
implementation of appropriate environmental pollution control and
mitigation measures. Site inspection findings were recorded in the site
inspection checklists and provided to the contractors to follow up. HSF
movements under the SkyPier Plan were audited, showing compliance with speed
limits. Bi-weekly audit of the MSS were conducted, ensuring the contractors
full complied with the requirements of the MTRMP-CAV.
The
recommended environmental mitigation measures, as included in the EM&A
programme, were effectively implemented during the reporting period. Also, the
EM&A programme implemented by the ET has effectively monitored the
construction activities and ensured the proper implementation of mitigation
measures.
[1] The
Manual is available on the Project’s dedicated website (accessible at:
http://env.threerunwaysystem.com/en/index.html)